Shortcut:
If P, Q and R can do a work in x, y and z days respectively then all of them working together can finish the work in
xyz
/
xy + yz + zx
days
Here, x = 6, y = 12, z = 24
Using these values in shortcut, we get:
=
6 x 12 x 24
/
6 x 12 + 12 x 24 + 24 x 6
=
6 x 12 x 24
/
72 + 288 + 144
=
6 x 12 x 24
/
504
=
24
/
7
= 3
3
/
7
Hence, they will take 3
3
/
7
days.
|